At Long Last, Construction Begins on CityPlace Burlington Site

By

Published November 15, 2022 at 3:17 p.m.


Mayor Miro Weinberger (second from left) and the CityPlace Burlington team - COURTNEY LAMDIN ©️ SEVEN DAYS
  • Courtney Lamdin ©️ Seven Days
  • Mayor Miro Weinberger (second from left) and the CityPlace Burlington team
For the first time in four years, there's movement at the Pit.

CityPlace Burlington, the long-stalled project in the center of Burlington’s downtown, was an active construction site on Tuesday morning. A crew of hard-hatted workers busied themselves at the site's entrance along Bank Street. An excavator scraped up mounds of dirt as dump trucks rumbled past, at one point prompting a gaggle of reporters to hastily make way.

To Mayor Miro Weinberger, these were the sights and sounds of progress after years of delay.



“I’ve always believed in this project,” he said. “This is what we need to make our downtown healthy and vibrant decades into the future.”

The activity was a major milestone for CityPlace, which has overcome legal battles, changes of ownership and redesigns since first being proposed in 2014. At that point, then-owner Don Sinex promised to replace the former Burlington Town Center mall with two 14-story towers of shops, apartments and a hotel. He began demolishing the mall in 2017, but little has happened on the site since that worked wrapped up in 2018, earning it the derisive nickname “the Pit.”
The CityPlace construction site - COURTNEY LAMDIN ©️ SEVEN DAYS
  • Courtney Lamdin ©️ Seven Days
  • The CityPlace construction site
Sinex sold his shares of the project in May to three local businessmen: Dave Farrington of Farrington Construction, Al Senecal of Omega Electric Construction and Scott Ireland of S.D. Ireland, all of whom joined the mayor at the site on Tuesday morning to describe their plans.

Once complete, CityPlace will consist of two buildings of about 10 stories with 427 apartments, including affordable units that will be managed by the Champlain Housing Trust. Plans call for ground-level retail, 422 parking spaces, and a rooftop restaurant and observation deck.

On Tuesday, crews were preparing for a new foundation, which will be poured by December 1. Construction will continue through the winter, with a goal to finish the so-called “South Building” on Bank Street in 2024.

The U-shaped “North Building” on Cherry Street, which includes the CHT units, would be complete by summer 2025. At that point, work would begin to rebuild portions of St. Paul and Pine streets that were severed from the city grid by the former mall. The developers aim to finish construction by November 2025.
The partners still don’t have financing for the entire project, however. Farrington said the team “has commitments” to finance the South Building but is talking “with some potential co-development partners” about funding the North Building. Champlain Housing Trust is separately seeking financing for the affordable housing portion.

Farrington estimates a total construction cost of $200 million.

He thanked the mayor's office and his fellow partners for getting the project going.

"It's been seven months and a lot of meetings," Farrington said. "We get a to-do list, and we break it up and just pick it apart and get it done. And that's the way this project is gonna keep moving."
CityPlace partner Dave Farrington and Mayor Miro Weinberger - COURTNEY LAMDIN ©️ SEVEN DAYS
  • Courtney Lamdin ©️ Seven Days
  • CityPlace partner Dave Farrington and Mayor Miro Weinberger
Correction, November 15, 2022: A previous version of this story misreported the length of time since work stopped at the site.

Related Stories

Speaking of...

Tags

Comments

Comments are closed.

From 2014-2020, Seven Days allowed readers to comment on all stories posted on our website. While we've appreciated the suggestions and insights, right now Seven Days is prioritizing our core mission — producing high-quality, responsible local journalism — over moderating online debates between readers.

To criticize, correct or praise our reporting, please send us a letter to the editor or send us a tip. We’ll check it out and report the results.

Online comments may return when we have better tech tools for managing them. Thanks for reading.